Offsite Improvement Permits

Offsite Improvement Permits

Offsites – Improvement Plans Review

The offsites team under the Development Review Division is responsible for providing professional and technical services specifically related to the review of improvement plans from developers in public right-of-way and easements. The offsites team issues permits for approved plans and manages revisions of approved plans. A typical offsite review includes verification of land use conditions, final maps, easements, pavement design and compliance with drainage, structural, traffic, design division, inter-agency concurrence, utility companies and BLM criteria.

Note: Once permit has been issued, refer to Construction Management tab for traffic control permits, inspections and bond release information.

Offsite Submittal Requirements

Drainage study, traffic study and structural review are to be approved before submittal. A Public Works Geotechnical review needs to be submitted for preliminary pavement sections after offsite is submitted.

First Review Submittal

  1. Submittal Sheet
  2. Copy of traffic study approval letter (if required by NOFA)
  3. Copy of drainage study approval letter and APPlans (if required by NOFA)
  4. Copy of Public Works structural approval letter and APSTRPlans (if required)
  5. 3 sets of improvement plans (stamped, signed and dated)
  6. Bond estimate
  7. Plan check fees as listed on the bond estimate. (Minimum is $300)

Subsequent Review Submittal

  1. Submittal Sheet
  2. 2 sets of improvement plans (stamped, signed and dated)
  3. Drainage study APPlans (if applicable)
  4. Structural APSTRPlans (if applicable)
  5. Bond estimate- revised (if NOT approved the first time)
  6. All previous redlines

Final Review Submittal

  1. Submittal Sheet
  2. 1 set of Mylars OR bond copy with all required signatures (stamped, signed and dated)
    Note: IP Plans and Map must match for permit to be issued.
  3. Drainage study APPlans (if applicable)
  4. Structural APSTRPlans (if applicable)
  5. All previous redlines

Offsite Revision Submittal Requirement

  1. Submittal Sheet
  2. Items listed on the Revision Checklist